Electric Era successfully installed six 200-kWh EV charging stalls at a Costco Wholesale in North Port, Florida, completing the project in a record 54 days.
The deployment highlights Electric Era's proprietary battery-backed architecture, which significantly reduces grid input power needs by up to 70%, enhancing efficiency.
Each charging unit supports both CCS and NACS connectors, offering a typical 80% charge within 20 to 60 minutes, catering to diverse EV models.
The integrated 32-inch touchscreens allow for retailer branding, loyalty program access, and direct integration with point-of-sale systems, enhancing customer engagement.
Electric Era, a Seattle-based charging solutions provider, has completed the rapid deployment of six 200-kWh electric vehicle (EV) charging stalls at a Costco Wholesale location in North Port, Florida. The project, which commenced on April 7, concluded with the site going live on May 30, marking an impressive 54-day turnaround from initiation to operational status. This swift execution underscores Electric Era's capabilities in accelerating critical EV infrastructure development, a key factor in the burgeoning EV market.
The expedited timeline saw permit applications and drawings submitted by April 18, with hardware arriving on-site by mid-May. The subsequent installation and testing phase was completed in just 10 days, culminating in final inspection approval and activation on May 30. This efficiency contrasts sharply with typical EV charging deployments, which often face extended timelines due to grid connection complexities and permitting processes.
Quincy Lee, CEO of Electric Era, emphasized the company's commitment to delivering efficient and reliable charging systems for retail partners. "Our retail customers want fast, reliable EV charging systems to help them grow their business and boost their bottom line," Lee stated. "We’re able to deliver a significantly more efficient process across the board and complete deployments at a fraction of the time it takes other EV charger manufacturers." This rapid deployment model is particularly attractive to retailers like Costco, who seek to quickly integrate value-added services for their customer base without prolonged construction disruptions.
A core technological advantage cited by Electric Era is its proprietary battery-backed architecture. This innovative design reduces the required grid input power by up to 70%, mitigating strain on local electrical infrastructure and potentially lowering installation costs and permitting hurdles associated with high-power grid connections. Each of the three charging units installed at Costco is equipped with both CCS and NACS connectors, ensuring compatibility with a wide range of EV models. Drivers can anticipate achieving an 80% charge within 20 to 60 minutes, aligning with consumer expectations for convenient and timely charging experiences.
Beyond the technical specifications, Electric Era's charging stations are designed with retail integration in mind. The 32-inch touchscreen interfaces allow for seamless integration of retailer branding, promotional content, and direct access to loyalty programs. Furthermore, the operating system integrates with existing retail IT platforms, enabling the collection of point-of-sale and CRM data. This strategic integration positions EV charging as more than just a utility, transforming it into a tool for customer attraction and retention, thereby enhancing the overall retail experience and providing new revenue streams for host businesses. The successful North Port deployment serves as a compelling case study for future retail and commercial EV charging expansions across the United States.