Back to Topics
Solar Energy

NTPC Green Energy Adds Nearly 100 MW to Solar Capacity, Bolstering India's Renewable Energy Portfolio in Gujarat

2 days ago
5 min read
1 news sources
Share:
NTPC Green Energy Adds Nearly 100 MW to Solar Capacity, Bolstering India's Renewable Energy Portfolio in Gujarat

Key Insights

  • NTPC Green Energy Limited has commissioned approximately 100 megawatts of new solar power capacity across two major projects in Khavda, Gujarat.

  • This includes 32.8 MW from the 300 MW Khavda Solar Energy Project and 64.7 MW from the 1,255 MW Khavda-I Solar Photovoltaic Project.

  • The recent additions contribute significantly to NTPC's expanding renewable energy footprint and India's ambitious clean energy targets.

  • These projects underscore Khavda's emerging role as a critical hub for large-scale solar power generation in the country.

New Delhi – NTPC Green Energy Limited (NGEL), a subsidiary of state-owned power giant NTPC, has announced the commissioning of nearly 100 megawatts (MW) of additional solar power capacity in Khavda, Gujarat. This significant expansion, detailed in a recent regulatory filing by NTPC, underscores the company's aggressive push towards bolstering India's renewable energy infrastructure and achieving its ambitious clean energy targets. The new capacity additions are strategically located within the vast Khavda region, a burgeoning hub for utility-scale solar projects.

The commissioned capacity comprises two distinct tranches. Firstly, 32.8 MW has been brought online as part of the larger 300 MW Khavda Solar Energy Project, which falls under NTPC Renewable Energy's 450 MW Hybrid Tranche-V initiative. This specific segment commenced commercial operations on January 30, 2025, following an earlier 142.2 MW addition on June 28, 2024. This phased commissioning strategy allows for efficient integration into the grid and optimized project execution.

Secondly, NGEL initiated commercial operations for 64.7 MW of the expansive 1,255 MW Khavda-I Solar Photovoltaic Project. This project, developed under the Central Public Sector Undertaking (CPSU) Scheme Phase-II Tranche-III, declared its latest segment operational on June 30, 2025. Previous phases of this mega-project, totaling 110.25 MW and 146.7 MW, had already commenced operations on June 6, 2025, and June 28, 2025, respectively. The continuous rollout of capacity from Khavda-I highlights the scale and speed of development in this critical solar zone.

These additions are pivotal for NTPC, which aims to significantly increase its green energy portfolio as part of India's broader energy transition strategy. The Khavda region, with its high solar insolation and vast barren land, is being transformed into one of the world's largest renewable energy parks. The successful commissioning of these projects reinforces NTPC Green Energy's position as a key player in India's renewable energy landscape, contributing directly to the nation's goal of achieving 500 GW of non-fossil fuel-based energy capacity by 2030. The consistent progress in Khavda is expected to attract further investment and technological advancements in the region.